[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930826":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},930826,602,1,"单选题","如果工程未能通过竣工试验导致工程价值降低，但合同价格应予减少的扣减金额的方法在合同中没有说明，经双方协商确定后，承包商应在( )前将扣减金额支付给业主，或根据业主的索赔约定支付。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","重新试验",false,{"key":16,"text":17,"correct":14},"B","承包商提交试验报告",{"key":19,"text":20,"correct":14},"C","工程师认可试验结果",{"key":22,"text":23,"correct":24},"D","签发接收证书",true,"",{"id":6,"name":27,"category":28,"favorite":29},"设备监理合同管理","建筑工程",0]