[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930825":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},930825,602,1,"单选题","设备采购合同，供货方负责代运设备的，交付设备日期以( )的日期为准。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","发运设备时承运部门签发设备单上的戳记",true,{"key":16,"text":17,"correct":18},"B","采购方收到设备",false,{"key":20,"text":21,"correct":18},"C","采购方在承运部门签收设备单上签收",{"key":23,"text":24,"correct":18},"D","供货方将设备交到承运部门","供货方负责代运货物的，以发货时承运部门签发货单上的戳记日期为准。",{"id":6,"name":27,"category":28,"favorite":29},"设备监理合同管理","建筑工程",0]