[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930818":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},930818,602,1,"单选题","承包商按照工程师的指示更新了进度计划，并按照新的进度计划实施设备工程。承担由此带来的风险和费用的是( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","工程师承担风险，承包商承担费用",false,{"key":16,"text":17,"correct":14},"B","工程师承担风险，业主承担费用",{"key":19,"text":20,"correct":21},"C","承包商承担风险和费用",true,{"key":23,"text":24,"correct":14},"D","业主承担风险和费用","",{"id":6,"name":27,"category":28,"favorite":29},"设备监理合同管理","建筑工程",0]