[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930808":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},930808,602,1,"单选题","如果承包商隐蔽已经完成的工作前未通知工程师进行检验，则当工程师提出剥露检验要求时，承担由于检验所产生的费用的是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","业主",false,{"key":16,"text":17,"correct":18},"B","承包商",true,{"key":20,"text":21,"correct":14},"C","工程师",{"key":23,"text":24,"correct":14},"D","如果检验的结果证明完成的隐蔽工程符合合同要求，则由业主承担全部费用，否则，将由承包商承担全部费用","",{"id":6,"name":27,"category":28,"favorite":29},"设备监理合同管理","建筑工程",0]