[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930804":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},930804,602,1,"单选题","承包商应在设备工程或单位工程的( )之前，按照业主要求完成所有的缺陷或损坏部分的修补。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","竣工时间",false,{"key":16,"text":17,"correct":18},"B","缺陷通知期期满",true,{"key":20,"text":21,"correct":14},"C","颁发接收证书",{"key":23,"text":24,"correct":14},"D","保留金返还","",{"id":6,"name":27,"category":28,"favorite":29},"设备监理合同管理","建筑工程",0]