[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930803":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},930803,602,1,"单选题","某工程双方按口头协议委托的施工任务，但双方一直没有签订书面合同。在施工任务完成后由于发包人拖欠工程款而发生纠纷，此时应当认定( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","尚无合同关系",false,{"key":16,"text":17,"correct":14},"B","合同没有成立",{"key":19,"text":20,"correct":21},"C","合同已经成立",true,{"key":23,"text":24,"correct":14},"D","由于法律规定建设工程合同应当采用书面形式，故发包人不承担责任","属于合同形式欠缺。虽然法律规定工程合同采用书面形式，但当事人未采用书面形式，并且一方已经履行了主要义务，对方接受的，该合同成立。",{"id":6,"name":27,"category":28,"favorite":29},"设备监理合同管理","建筑工程",0]