[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930797":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},930797,602,1,"单选题","设备工程合同履行过程中合同调整的技术措施是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","增加人员投入",false,{"key":16,"text":17,"correct":18},"B","变更工程设计",true,{"key":20,"text":21,"correct":14},"C","加大资金收入",{"key":23,"text":24,"correct":14},"D","调整合同计划","技术措施一般是指在施工过程中采取先进的施工方法，或变更设计方案，对设计方案进行优化，使用先进的设备，改变施工工艺等来实现进度和质量目标的措施。",{"id":6,"name":27,"category":28,"favorite":29},"设备监理合同管理","建筑工程",0]