[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930786":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},930786,602,1,"单选题","如果承包商延误工程竣工试验且在收到工程师通知后21天内未进行竣工试验，业主人员自行进行了相应试验。下列对此试验的风险和费用承担的说法，正确的是( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","工程合格，承包商承担风险，业主承担费用",false,{"key":16,"text":17,"correct":14},"B","工程合格，业主承担风险和费用",{"key":19,"text":20,"correct":14},"C","工程不合格，业主承担风险，承包商承担费用",{"key":22,"text":23,"correct":24},"D","无论试验结果如何，均由承包商承担风险和费用均由承包商承担",true,"",{"id":6,"name":27,"category":28,"favorite":29},"设备监理合同管理","建筑工程",0]