[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930779":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},930779,602,1,"单选题","FIDIC“新黄皮书”规定，开工日期应在( )的42天内。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","承包商提交履约担保后",false,{"key":16,"text":17,"correct":18},"B","承包商收到中标函后",true,{"key":20,"text":21,"correct":14},"C","工程师发出开工通知后",{"key":23,"text":24,"correct":14},"D","双方签订合同后","",{"id":6,"name":27,"category":28,"favorite":29},"设备监理合同管理","建筑工程",0]