[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930772":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},930772,602,1,"单选题","采用FIDIC合同条件的设备工程合同，对承包商的设备进行投保时，保险有效期限是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","设备起运日起，至设备离开现场",true,{"key":16,"text":17,"correct":18},"B","设备运抵现场起，至使用该设备的工程竣工",false,{"key":20,"text":21,"correct":18},"C","开工之日起，至颁发接收证书",{"key":23,"text":24,"correct":18},"D","开工之日起，至竣工时间届满","",{"id":6,"name":27,"category":28,"favorite":29},"设备监理合同管理","建筑工程",0]