[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930761":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},930761,602,1,"单选题","采用FIDIC合同条件的设备工程合同，实施工程的费用发生波动，根据合同的价格调整规定，对因市场价格变化不能完全得到补偿时，( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","工程师应确定一个费用指数，重新价格调整的数额",false,{"key":16,"text":17,"correct":14},"B","获得现行费用指数后，重新计算价格调整的数额",{"key":19,"text":20,"correct":21},"C","应被认为在中标合同金额中已经包含了这一部分物价波动的风险费",true,{"key":23,"text":24,"correct":14},"D","应被认为已经按照合同中规定的调价公式予以了调整","",{"id":6,"name":27,"category":28,"favorite":29},"设备监理合同管理","建筑工程",0]