[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930748":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},930748,602,1,"单选题","由于业主原因造成竣工试验的延误，承包商有权获得的补偿是( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","竣工时间",false,{"key":16,"text":17,"correct":14},"B","费用",{"key":19,"text":20,"correct":21},"C","费用和利润",true,{"key":23,"text":24,"correct":14},"D","竣工时间、费用和利润","",{"id":6,"name":27,"category":28,"favorite":29},"设备监理合同管理","建筑工程",0]