[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930746":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},930746,602,1,"单选题","设备工程合同的计价方式不同，双方当事人的风险分担不同，承包商承担风险最多的合同计价方式是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工程量清单合同",false,{"key":16,"text":17,"correct":18},"B","固定总价合同",true,{"key":20,"text":21,"correct":14},"C","成本加固定费用",{"key":23,"text":24,"correct":14},"D","混合合同","",{"id":6,"name":27,"category":28,"favorite":29},"设备监理合同管理","建筑工程",0]