[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930742":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},930742,602,1,"单选题","执行政府指导价的合同，当事人一方逾期提货时恰遇政府指导价格上涨，应按( )执行",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","原价格",false,{"key":16,"text":17,"correct":18},"B","新价格",true,{"key":20,"text":21,"correct":14},"C","原价和新价的平均价格",{"key":23,"text":24,"correct":14},"D","当地市场价格","执行政府定价或者政府指导价的，在合同约定的交付期限内政府价格调整时，按照交付时的价格计价。逾期交付标的物的，遇价格上涨时，按照原价格执行；价格下降时，按照新价格执行。逾期提取标的物或者逾期付款的，遇价格上涨时，按照新价格执行；价格下降时，按照原价格执行。",{"id":6,"name":27,"category":28,"favorite":29},"设备监理合同管理","建筑工程",0]