[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930726":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},930726,602,1,"单选题","下列关于承包商暂停工作权利的说法，错误的是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","如果业主未能按照合同规定的时间支付进度款，承包商即可暂停工作",true,{"key":16,"text":17,"correct":18},"B","暂停工作不影响承包商对延迟付款获得融资费用和终止合同的权利用",false,{"key":20,"text":21,"correct":18},"C","如果承包商暂停工作致使工期和费用受到影响，工程师应公正确定对承包商的补偿",{"key":23,"text":24,"correct":18},"D","如果承包商因放慢工作进度致使工期和费用受到影响，可以提出工期延长及补偿费用和利润的要求","",{"id":6,"name":27,"category":28,"favorite":29},"设备监理合同管理","建筑工程",0]