[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930722":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},930722,602,1,"单选题","按照FIDIC新黄皮书对工程接收程序的规定，工程竣工的日期应当是( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","承包商完成全部工程的日期",false,{"key":16,"text":17,"correct":14},"B","工程通过竣工试验的日期",{"key":19,"text":20,"correct":14},"C","工程师签发接收证书的日期",{"key":22,"text":23,"correct":24},"D","接收证书中注明的竣工的日期",true,"",{"id":6,"name":27,"category":28,"favorite":29},"设备监理合同管理","建筑工程",0]