[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930709":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},930709,602,1,"单选题","根据《建设工程质量管理条例》的规定，施工人员对钢筋混凝土梁中用到的钢筋取样时，应当在( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","建设单位的监督下取样，并送交监理人员检测",false,{"key":16,"text":17,"correct":14},"B","监理人员的监督下取样，并送交建设单位检测",{"key":19,"text":20,"correct":14},"C","设计单位的监督下现场取样，并送具有相应资质等级的质量检测单位进行检测",{"key":22,"text":23,"correct":24},"D","建设单位或者监理单位监督下现场取样，并送具有相应资质等级的质量检测单位进行检测",true,"",{"id":6,"name":27,"category":28,"favorite":29},"设备监理合同管理","建筑工程",0]