[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930700":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},930700,602,1,"单选题","如果业主不合理地拖延竣工后试验，由此产生的损失，承包商有权索赔( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","竣工时间及相关费用",false,{"key":16,"text":17,"correct":18},"B","相关费用并加合理利润",true,{"key":20,"text":21,"correct":14},"C","竣工时间、相关费用并加合理利润",{"key":23,"text":24,"correct":14},"D","缺陷通知期及相关费用","",{"id":6,"name":27,"category":28,"favorite":29},"设备监理合同管理","建筑工程",0]