[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930697":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},930697,602,1,"单选题","设备工程安装中，如果由采购方负责设备安装调试，则供货方的现场服务内容不应包括( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","提供现场的地下管线资料",true,{"key":16,"text":17,"correct":18},"B","派出必要的现场服务人员",false,{"key":20,"text":21,"correct":18},"C","重要工序须经供货方现场技术人员签字确定",{"key":23,"text":24,"correct":18},"D","整个安装调试过程应在供货方现场人员指导下进行","安装调试过程中，若采购方未依照供货方的技术资料规定和现场服务人员的指导、未经现场供货技术服务人员签字确认出现的问题，采购方自行负责(设备质量问题除外)。",{"id":6,"name":27,"category":28,"favorite":29},"设备监理合同管理","建筑工程",0]