[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930695":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},930695,602,1,"单选题","工程师基于非承包商原因指示承包商暂停实施某一部分或全部设备工程后，负责对工程做好保护措施的是( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","工程师",false,{"key":16,"text":17,"correct":14},"B","业主",{"key":19,"text":20,"correct":21},"C","承包商",true,{"key":23,"text":24,"correct":14},"D","造成工程暂停的责任方","",{"id":6,"name":27,"category":28,"favorite":29},"设备监理合同管理","建筑工程",0]