[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930691":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},930691,602,1,"单选题","如果由于非承包商原因导致竣工后试验未能在缺陷通知期(或双方商定的其他期限)内完成，则( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","承包商另行选择日期进行竣工后试验",false,{"key":16,"text":17,"correct":18},"B","此设备工程或单位工程应被认为已通过了竣工后试验",true,{"key":20,"text":21,"correct":14},"C","缺陷通知期后，工程师再安排竣工后试验",{"key":23,"text":24,"correct":14},"D","双方商定其他期限，完成竣工后试验","",{"id":6,"name":27,"category":28,"favorite":29},"设备监理合同管理","建筑工程",0]