[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930684":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},930684,602,1,"单选题","如果规定必须在工程接收之前完成对业主的人员进行工程操作和维修方面的培训，则完成培训是( )的构成条件之一。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","进行工程竣工试验",false,{"key":16,"text":17,"correct":18},"B","工程接收",true,{"key":20,"text":21,"correct":14},"C","进行工程竣工后试验",{"key":23,"text":24,"correct":14},"D","签发履约证书","",{"id":6,"name":27,"category":28,"favorite":29},"设备监理合同管理","建筑工程",0]