[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930683":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},930683,602,1,"单选题","采用FIDIC合同条件的设备工程合同，无论工程师采取何种方式提出变更，应在( )之前。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","开工日期",false,{"key":16,"text":17,"correct":14},"B","签发付款证书",{"key":19,"text":20,"correct":21},"C","签发接收证书",true,{"key":23,"text":24,"correct":14},"D","签发履约证书","",{"id":6,"name":27,"category":28,"favorite":29},"设备监理合同管理","建筑工程",0]