[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930674":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},930674,602,1,"单选题","FIDIC“新黄皮书”中，按合同规定的计量方法，实际支付给承包商的金额是( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","进度款",false,{"key":16,"text":17,"correct":14},"B","结算款",{"key":19,"text":20,"correct":21},"C","合同价格",true,{"key":23,"text":24,"correct":14},"D","保留金","",{"id":6,"name":27,"category":28,"favorite":29},"设备监理合同管理","建筑工程",0]