[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930671":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},930671,602,1,"单选题","根据FIDIC《设计采购施工(EP C)／交钥匙工程合同》的规定，在颁发工程接收证书前的任何时间，( )可通过发布指示或要求承包商提交建议书的方式，提出变更。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","工程师",false,{"key":16,"text":17,"correct":14},"B","工程师助手",{"key":19,"text":20,"correct":21},"C","雇主",true,{"key":23,"text":24,"correct":14},"D","雇主代表","这属于雇主的变更权。在颁发工程接收证书前的任何时间，雇主可通过发布指示或要求承包商提交建议书的方式，提出变更。",{"id":6,"name":27,"category":28,"favorite":29},"设备监理合同管理","建筑工程",0]