[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930663":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},930663,602,1,"单选题","建设单位因故不能按期开工的，应当向发证机关申请延期，经延期，建筑工程施工许可证的有效期限最长可达到( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","三个月",false,{"key":16,"text":17,"correct":14},"B","六个月",{"key":19,"text":20,"correct":21},"C","九个月",true,{"key":23,"text":24,"correct":14},"D","一年","建设单位应当自领取施工许可证之日起3个月内开工。因故不能按期开工的，应当向发证机关申请延期；延期以两次为限，每次不超过3个月。",{"id":6,"name":27,"category":28,"favorite":29},"设备监理合同管理","建筑工程",0]