[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930652":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},930652,602,1,"单选题","承包商按照合同要求编制的竣工文件，应保存在现场，并在( )，提交工程师两套副本。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","移交工程时",false,{"key":16,"text":17,"correct":18},"B","竣工试验开始前",true,{"key":20,"text":21,"correct":14},"C","通过竣工试验后",{"key":23,"text":24,"correct":14},"D","申请签发接收证书时","",{"id":6,"name":27,"category":28,"favorite":29},"设备监理合同管理","建筑工程",0]