[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930639":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},930639,602,1,"单选题","设备工程完工后，( )应组织对设备工程项目进行验收。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","业主",true,{"key":16,"text":17,"correct":18},"B","设备监理工程师",false,{"key":20,"text":21,"correct":18},"C","设计人",{"key":23,"text":24,"correct":18},"D","承包人","一般在设备工程完工时，业主应组织各方人员对设备工程项目进行验收。验收时会提出很多的不符合项，要求承包商消缺，且每个消缺项完成后，业主需认可签字。直到全部的消缺项被认可后，方可认为合同的主体工程完成。",{"id":6,"name":27,"category":28,"favorite":29},"设备监理合同管理","建筑工程",0]