[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930635":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},930635,602,1,"单选题","采用FIDIC合同条件的设备工程合同，承包商因不可抗力索赔工期的，应在不可抗力发生后的( )天，向工程师发出通知。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","7",false,{"key":16,"text":17,"correct":14},"B","14",{"key":19,"text":20,"correct":21},"C","28",true,{"key":23,"text":24,"correct":14},"D","42","",{"id":6,"name":27,"category":28,"favorite":29},"设备监理合同管理","建筑工程",0]