[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930623":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},930623,602,1,"单选题","某建设工程施工总承包单位经建设单位认可，将电气线路安装进行了分包。工程竣工验收中，发现电气线路安装质量不符合工程设计要求，存在安全隐患，导致工程未能通过竣工验收。对此，下列说法正确的是( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","建设单位认可了总承包单位的分包，总承包单位对电气线路安装质量不承担责任",false,{"key":16,"text":17,"correct":14},"B","电气线路安装不符合工程设计要求导致工程竣工延误，应由分包人向建设单位承担工程竣工延误的责任",{"key":19,"text":20,"correct":14},"C","分包人应当向建设单位承担电气线路安装的返修、保修责任",{"key":22,"text":23,"correct":24},"D","总承包单位不仅对电气线路承担维修责任，还应承担由此导致的工期延误的责任",true,"",{"id":6,"name":27,"category":28,"favorite":29},"设备监理合同管理","建筑工程",0]