[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930618":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},930618,602,1,"单选题","采用FIDIC合同条件的设备工程合同，在( )后，因法律变化引起工程费用增加的，应相应调整合同价格。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","基准日期",true,{"key":16,"text":17,"correct":18},"B","合同生效",false,{"key":20,"text":21,"correct":18},"C","工程师通知开工",{"key":23,"text":24,"correct":18},"D","开工日期","",{"id":6,"name":27,"category":28,"favorite":29},"设备监理合同管理","建筑工程",0]