[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930616":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},930616,602,1,"单选题","工程师收到承包商的签发接收证书申请后，未在( )天内作出答复，而工程或单位工程(视情况而定)实质上符合合同要求，应认为在上述期限的最后一天已经签发了接收证书。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","14",false,{"key":16,"text":17,"correct":18},"B","28",true,{"key":20,"text":21,"correct":14},"C","42",{"key":23,"text":24,"correct":14},"D","56","",{"id":6,"name":27,"category":28,"favorite":29},"设备监理合同管理","建筑工程",0]