[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930611":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},930611,602,1,"单选题","设备工程合同生效后，设备工程合同的变更，( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","不能出自于业主的要求",false,{"key":16,"text":17,"correct":14},"B","不能出自于承包商的建议",{"key":19,"text":20,"correct":14},"C","只能出自于监理工程师的建议",{"key":22,"text":23,"correct":24},"D","既可以出自于业主的要求，也可以来自于承包商的建议",true,"业主可以提出变更要求，要求承包商按变更实施，承包商也可以提合理化建议，业主可以酌情考虑。设备工程合同的变更既可能出自业主的要求，也可能来自承包商提出建议。",{"id":6,"name":27,"category":28,"favorite":29},"设备监理合同管理","建筑工程",0]