[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930604":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},930604,602,1,"单选题","某设备工程项目的投标人在现场踏勘后以书面形式提出质疑问题，招标人离开标时间还剩10天才作出了书面解答。鉴于解答时间短于《招标投标法》规定的时间，且书面解答与招标文件规定内容不一致，对该问题应以( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","招标文件为准，开标时间后延",false,{"key":16,"text":17,"correct":14},"B","招标文件为准，开标时间不变",{"key":19,"text":20,"correct":21},"C","书面解答为准，开标时间后延",true,{"key":23,"text":24,"correct":14},"D","书面解答为准，开标时间不变","招标人对已发出的招标文件进行必要的澄清或者修改的，应当在招标文件要求提交投标文件截止时间至少15日前，以书面形式通知所有招标文件收受人。不足15日的，招标人应当顺延投标文件的截止时间。该澄清或者修改的内容为招标文件的组成部分。",{"id":6,"name":27,"category":28,"favorite":29},"设备监理合同管理","建筑工程",0]