[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930601":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},930601,602,1,"单选题","由于业主原因造成未经竣工试验而接收工程，应在缺陷通知期内进行竣工试验的，工程师应按提前( )天通知承包商进行竣工试验的日期。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","7",false,{"key":16,"text":17,"correct":18},"B","14",true,{"key":20,"text":21,"correct":14},"C","21",{"key":23,"text":24,"correct":14},"D","28","",{"id":6,"name":27,"category":28,"favorite":29},"设备监理合同管理","建筑工程",0]