[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930600":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},930600,602,1,"单选题","对基准点、基准线和基准标高等原始数据的错误，应由( )承担责任。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工程师",false,{"key":16,"text":17,"correct":18},"B","业主",true,{"key":20,"text":21,"correct":14},"C","承包商",{"key":23,"text":24,"correct":14},"D","分包商","",{"id":6,"name":27,"category":28,"favorite":29},"设备监理合同管理","建筑工程",0]