[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930583":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},930583,602,1,"单选题","在设备工程合同履行中，属于业主索赔事由的是( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","设备监理工程师要求增加工程量，致使业主受到损失",false,{"key":16,"text":17,"correct":14},"B","设备监理工程师批示错误，致使业主受到损失",{"key":19,"text":20,"correct":14},"C","因设备监理工程师原因造成工程未能进行中间验收，致使业主受到损失",{"key":22,"text":23,"correct":24},"D","因分包商过错，致使业主受到损失",true,"工程师属于业主人员，他的错误行为不应引起业主索赔；分包商接受承包商管理，如有过错，可以引起业主向承包商的索赔。",{"id":6,"name":27,"category":28,"favorite":29},"设备监理合同管理","建筑工程",0]