[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930574":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},930574,602,1,"单选题","如果工程师的指示导致承包商因提供合作发生了某些不可预见费用，则该项指示应构成( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","合同文件",false,{"key":16,"text":17,"correct":14},"B","索赔",{"key":19,"text":20,"correct":14},"C","争议",{"key":22,"text":23,"correct":24},"D","变更",true,"",{"id":6,"name":27,"category":28,"favorite":29},"设备监理合同管理","建筑工程",0]