[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930550":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},930550,601,2,"多选题","根据《设备工程监理规范》，设备监理单位在设备设计过程中的工作内容有( )。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","参与审查被监理单位提交的设计总体方案及进度计划",true,{"key":16,"text":17,"correct":14},"B","对设计关键阶段和关键节点进行监督和见证",{"key":19,"text":20,"correct":14},"C","检查各专业之间的组织接口和技术接口情况",{"key":22,"text":23,"correct":14},"D","适时对项目质量计划、有关质量体系文件执行情况进行抽查",{"key":25,"text":26,"correct":27},"E","当出现不合格时，要求被监理单位立即返工",false,"ABCD","",{"id":6,"name":31,"category":32,"favorite":33},"设备工程监理基础及相关知识","建筑工程",0]