[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930545":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},930545,601,2,"多选题","在项目实施过程中，可能引起对设备的设计进行变更或修改的原因包括( )。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","设计评审、设计验证或设计确认要求变更",true,{"key":16,"text":17,"correct":14},"B","业主或分承包商对设备的性能或可靠性有新的要求",{"key":19,"text":20,"correct":14},"C","有关健康、安全、材料使用方面的法规要求发生了变化",{"key":22,"text":23,"correct":24},"D","监理人员要求更改",false,{"key":26,"text":27,"correct":14},"E","纠正措施或预防措施要求更改","ABCE","",{"id":6,"name":31,"category":32,"favorite":33},"设备工程监理基础及相关知识","建筑工程",0]