[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930533":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},930533,601,2,"多选题","根据一般设备制造过程的监理工作流程，在制造过程监理结束之后，需要完成的后续工作是( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","检查技术文件的准备情况",false,{"key":16,"text":17,"correct":18},"B","整理监理资料，编写评估报告",true,{"key":20,"text":21,"correct":14},"C","检查工艺装备的状况",{"key":23,"text":24,"correct":14},"D","检查原材料、外协件和外购件的准备情况",{"key":26,"text":27,"correct":18},"E","组织出厂验收，编写监理总结报告","BE","",{"id":6,"name":31,"category":32,"favorite":33},"设备工程监理基础及相关知识","建筑工程",0]