[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930524":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},930524,601,2,"多选题","下列关于项目信息特点的说法，正确的有( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","项目信息的价值与提供的时间无关",false,{"key":16,"text":17,"correct":18},"B","信息是项目沟通的基本前提条件",true,{"key":20,"text":21,"correct":18},"C","信息是决策和管理的基础",{"key":23,"text":24,"correct":14},"D","项目信息数量庞大，很难用管理的系统方法分析、提取",{"key":26,"text":27,"correct":14},"E","知识是人类对主观意志的认识和掌握，是一种系统化的信息","BC","",{"id":6,"name":31,"category":32,"favorite":33},"设备工程监理基础及相关知识","建筑工程",0]