[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930515":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},930515,601,2,"多选题","下列关于项目管理各过程组工作内容的说法，正确的有( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","完成项目要解决问题的计划是在收尾过程组中确定的",false,{"key":16,"text":17,"correct":18},"B","项目或项目阶段的工作是在启动过程组中定义的",true,{"key":20,"text":21,"correct":18},"C","对执行偏差的纠正是监控过程组的工作",{"key":23,"text":24,"correct":14},"D","组织和协调项目各类资源和工作是规划过程组的工作",{"key":26,"text":27,"correct":14},"E","服务或成果的验收是执行过程组的工作","BC","",{"id":6,"name":31,"category":32,"favorite":33},"设备工程监理基础及相关知识","建筑工程",0]