[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930478":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},930478,601,2,"多选题","在编制设备工程进度计划时，确定各工作或活动持续时间的方法包括( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","类比估算法",true,{"key":16,"text":17,"correct":18},"B","自下而上汇总法",false,{"key":20,"text":21,"correct":14},"C","时间定额估算法",{"key":23,"text":24,"correct":18},"D","参数模型法",{"key":26,"text":27,"correct":14},"E","专家评定法","ACE","",{"id":6,"name":31,"category":32,"favorite":33},"设备工程监理基础及相关知识","建筑工程",0]