[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930477":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},930477,601,2,"多选题","在审查项目投资估算时，应注意审查( )。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","所采用资料的时效性.准确性",true,{"key":16,"text":17,"correct":14},"B","审查选用的投资估算方法的科学性.适用性",{"key":19,"text":20,"correct":14},"C","编制内容与拟建项目规划要求的一致性",{"key":22,"text":23,"correct":24},"D","节约投资措施的有效性",false,{"key":26,"text":27,"correct":14},"E","费用项目.费用数额的真实性","ABCE","",{"id":6,"name":31,"category":32,"favorite":33},"设备工程监理基础及相关知识","建筑工程",0]