[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930445":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},930445,601,2,"多选题","设备工程进度控制是对设备工程各阶段的相关部分根据其进度总目标及资源优化配置原则，编制计划并付诸实施、检查和调整的全部过程，这些部分包括( )。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","工作内容",true,{"key":16,"text":17,"correct":14},"B","工作顺序",{"key":19,"text":20,"correct":14},"C","工作持续时间",{"key":22,"text":23,"correct":24},"D","工作质量",false,{"key":26,"text":27,"correct":24},"E","工作实际进度","ABC","",{"id":6,"name":31,"category":32,"favorite":33},"设备工程监理基础及相关知识","建筑工程",0]