[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930433":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},930433,601,2,"多选题","在编制设备工程进度计划时，需要确定活动的持续时间，可以采用的方法包括( )。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","专家评定",true,{"key":16,"text":17,"correct":14},"B","类比估计",{"key":19,"text":20,"correct":14},"C","预留时间",{"key":22,"text":23,"correct":14},"D","时间定额估计法",{"key":25,"text":26,"correct":27},"E","WBS方法",false,"ABCD","",{"id":6,"name":31,"category":32,"favorite":33},"设备工程监理基础及相关知识","建筑工程",0]