[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930428":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},930428,601,2,"多选题","按计划的范围分类，设备工程进度计划包括( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","设计进度计划",false,{"key":16,"text":17,"correct":18},"B","设备工程总进度计划",true,{"key":20,"text":21,"correct":18},"C","设备工程前期工作进度计划",{"key":23,"text":24,"correct":14},"D","设备安装调试进度计划",{"key":26,"text":27,"correct":18},"E","部组件进度计划","BCE","",{"id":6,"name":31,"category":32,"favorite":33},"设备工程监理基础及相关知识","建筑工程",0]