[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930427":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},930427,601,2,"多选题","在解决设备工程项目中的物流冲突时，设备监理工程师应( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","首先考虑各方的价值补偿",false,{"key":16,"text":17,"correct":18},"B","首先保证物畅其流",true,{"key":20,"text":21,"correct":14},"C","首先向业主通报物流冲突的调查结果",{"key":23,"text":24,"correct":18},"D","检查业主在履行合同过程中有无违约问题",{"key":26,"text":27,"correct":18},"E","检查承包商在履行合同过程中有无非法变更问题","BDE","",{"id":6,"name":31,"category":32,"favorite":33},"设备工程监理基础及相关知识","建筑工程",0]