[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930346":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},930346,601,2,"多选题","一般的设备工程进度目标分解方法包括( )",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","按项目组成分解",true,{"key":16,"text":17,"correct":14},"B","按项目计划期分解",{"key":19,"text":20,"correct":21},"C","按项目紧急程度分解",false,{"key":23,"text":24,"correct":14},"D","按项目实施单位分解",{"key":26,"text":27,"correct":14},"E","按设备工程实施过程分解","ABDE","",{"id":6,"name":31,"category":32,"favorite":33},"设备工程监理基础及相关知识","建筑工程",0]